The general plan of realization from start to the beginning of generation in a network of solar power plant

  • signing of the Land Lease Agreement;
  • obtaining Technical conditions for connection to electrical networks;  
  • preparation of design documentation for SES;
  • obtaining urban planning conditions;
  • project expertise;
  • approval of project documentation at SES;
  • obtaining a permit to start construction;
  • preparation of design documentation for connection of SES to networks;
  • approval of project documentation for connection to the network;
  • arrangement of electric networks for delivery of power of station in a network;
  • arrangement of networks of own needs;
  • delivery of metal structures;
  • supply of inverters;
  • delivery of photomodules;
  • execution of construction and installation works on the SES site;
  • execution of commissioning works of SES equipment;
  • preparation of executive documentation;
  • obtaining a declaration of completion of construction works;
  • registration of documents for obtaining a license and a green tariff in the National Commission for Regulation of Economic Competition;
  • signing of the Agreement with Energorynok.